Gujarat fire safety fees depend on the building category. FSPA (plan approval) and FSCR (renewal) are flat fees. FSCA (certificate approval) is charged per m² of built-up area. Use the calculator below, then confirm the amount on the portal, which calculates the live figure and prevails over any table.

FSPA
Flat fee by category
FSCA
Rs per m² of built-up area
FSCR
Flat fee by category
Temporary structures
Rs 2,000 lump sum
Appeal
50% of the fee, within 15 days

Fee calculator

Choose a category to see the fees.

Late-fee estimate

Uses the category and area chosen above. N is the number of 90-day blocks, started or complete.

Indicative only. The portal calculates the amount that applies to you and prevails over this table. Source: 2022 portal Applicant Guide.

How the fees work

  • FSPA: flat fee for the fire safety plan approval, paid with the application.
  • FSCA: a rate in rupees per m² of built-up area, paid with the Form B14 application.
  • FSCR: flat fee for the renewal.
  • Temporary structures and pandals: an online checklist with a fee of Rs 2,000.
  • Appeal: 50 percent of the respective application fee, filed through the portal within 15 days of a rejection.

Annexure 8 of the 2023 Regulations sets the fees by category and says they are as the Government prescribes from time to time. The rows in this calculator come from the 2022 portal Applicant Guide, and the first rows match the 2023 gazette. Fees can have changed since.

How late fees are worked out

Regulation 11 charges late filings in blocks of 90 days, started or complete. N is the number of blocks:

Late filingCharge
Annual declarationN x 100% of the FSPA fee
Six-monthly declaration cum inspection reportN x 100% of the FSCR fee
Certificate renewalN x 25% of the FSCA fee

The portal guide's illustrations: 24 days late is 100 percent of the FSPA fee; 124 days late is 200 percent of the FSPA fee; a renewal 208 days late (90 + 90 + 28) is 3 x 25 percent of the FSCA fee.

The table and the portal guide say FSPA for the annual declaration, while the worked example in the 2023 Regulations says FSCA. The calculator follows the table and the guide. Check the amount on the portal.

Notes on the table

  • Rows C3I1 and C3I2 have the same band wording in the guide but different fees. Both are shown as printed.
  • Colleges, universities and technical institutes use the same three bands and fees as schools (C2ED1 to C2ED3).
  • The guide's storage rows start at 250 m² covered area. The checklists on the portal decide which category applies to your building.
  • Fire Safety Officer charges for renewals, inspections and drills are separate from government fees.

Full fee table

FSPA and FSCR are flat fees. FSCA is per m² of built-up area. Temporary structures and pandals: Rs 2,000 lump sum through the online checklist.

Category and bandCodeFSPAFSCA per m²FSCR
Residential (flats, hostels, dormitories)
15 to 35 mC1R1Rs 1,000Rs 10Rs 1,000
above 35 to 45 mC1R2Rs 2,500Rs 12Rs 2,500
above 45 to 60 mC1R3Rs 5,000Rs 15Rs 5,000
above 60 mC1R4Rs 7,000Rs 20Rs 7,000
Hotels below 5 star, motels, guest houses, dharamshala, resorts
under 15 m, floor over 500 and up to 1,000 m²C1R5Rs 1,500Rs 15Rs 1,500
under 15 m, floor over 1,000 m²C1R6Rs 2,500Rs 20Rs 2,500
15 to 30 mC1R7Rs 1,000Rs 10Rs 1,000
above 30 mC1R8Rs 5,000Rs 30Rs 5,000
5-star and above hotels and resorts
any heightC1R9Rs 7,000Rs 50Rs 7,000
Schools, colleges, universities, technical institutes
ground plus one or more with over 500 m² on a floor, or over 9 m and under 15 mC2ED1Rs 1,000Rs 7Rs 1,000
15 to 24 mC2ED2Rs 2,500Rs 10Rs 2,500
above 24 to 30 mC2ED3Rs 5,000Rs 10Rs 5,000
Hospitals, sanatoria, nursing homes
under 15 m, plot up to 1,000 m², up to ground plus one with bedsC3I1Rs 1,000Rs 7Rs 1,000
same band as C3I1, listed again in the guideC3I2Rs 1,500Rs 8Rs 1,500
under 15 m, plot over 1,000 m²C3I3Rs 1,000Rs 9Rs 1,000
15 m to under 24 mC3I4Rs 2,500Rs 10Rs 2,500
above 24 to 45 mC3I5Rs 5,000Rs 15Rs 5,000
Custodial, penal and mental facilities
under 10 m, up to 300 personsC3I6Rs 1,000Rs 7Rs 1,000
under 10 m, over 300 personsC3I7Rs 1,000Rs 7Rs 1,000
10 to 15 mC3I8Rs 2,500Rs 8Rs 2,500
15 to 24 mC3I9Rs 3,000Rs 10Rs 3,000
24 to 30 mC3I10Rs 5,000Rs 15Rs 5,000
Assembly (cinema, auditorium, banquet hall, religious, stadium and similar)
under 10 m, 50 to 300 personsC4A1Rs 1,000Rs 8Rs 1,000
under 10 m, over 300 personsC4A2Rs 1,500Rs 9Rs 1,500
above 10 to 15 mC4A3Rs 2,500Rs 12Rs 2,500
above 15 to 24 mC4A4Rs 3,000Rs 15Rs 3,000
above 24 to 30 mC4A5Rs 5,000Rs 20Rs 5,000
Shopping malls and shopping-cum-entertainment complexes
any area or heightC4A6Rs 5,000Rs 25Rs 5,000
Metro and mass transport systems
any area or heightC4A7Rs 7,000Rs 25Rs 7,000
Business and offices (offices, banks, labs, data centres, IT parks)
above 15 to 24 mC5B1Rs 1,000Rs 10Rs 1,000
above 24 to 30 mC5B2Rs 2,500Rs 15Rs 2,500
above 30 mC5B3Rs 5,000Rs 20Rs 5,000
Mercantile (stores, wholesale markets, large shopping complexes)
under 15 m, ground plus one, over 500 m²C6M1Rs 1,000Rs 10Rs 1,000
above 15 to 24 mC6M2Rs 2,500Rs 12Rs 2,500
above 24 to 30 mC6M3Rs 5,000Rs 15Rs 5,000
Underground shopping complex
any area or floorsC6M4Rs 5,000Rs 15Rs 5,000
Storage (godown, warehouse, cold storage, depot)
over 250 m² covered, under 15 m, ground floor onlyC8S1Rs 2,500Rs 10Rs 2,500
over 250 m² covered, under 15 m, ground plus oneC8S2Rs 2,500Rs 15Rs 2,500
over 250 m² covered, under 15 m, more than ground plus oneC8S3Rs 5,000Rs 20Rs 5,000
Multi-level vehicle parking
all typesC8S4Rs 5,000Rs 20Rs 5,000
Hazardous or flammable storage and handling (LPG, flammable liquids, petrol pump, gas station)
single storeyC9H1Rs 5,000Rs 20Rs 5,000
more than one floor but under 15 mC9H2Rs 7,000Rs 30Rs 7,000
Mixed use (business cum mercantile, residential cum commercial)
above 9 m or above ground plus twoC10MX1Rs 2,500Rs 10Rs 2,500
above 15 to 24 mC10MX2Rs 2,500Rs 10Rs 2,500
above 24 to 30 mC10MX3Rs 5,000Rs 20Rs 5,000
above 30 mC10MX4Rs 5,000Rs 20Rs 5,000

Common questions

How much is the Gujarat fire safety certificate fee?

It depends on the building category and, for the certificate itself, on built-up area. For example, a 15 to 35 m residential building pays Rs 1,000 for plan approval, Rs 10 per m² of built-up area for the certificate, and Rs 1,000 for renewal, per the 2022 portal guide. Use the calculator for other categories.

What is the fee for a pandal or temporary structure?

An online checklist with a fee of Rs 2,000.

How is the late fee calculated?

In blocks of 90 days. A late renewal is N x 25 percent of the FSCA fee, a late annual declaration is N x 100 percent of the FSPA fee, and a late six-monthly report is N x 100 percent of the FSCR fee.

More questions? See the fire safety FAQ for short answers on certificates, renewal, penalties, extinguishers and pandals.

Plan the equipment budget too

Government fees are one part of the cost. The certificate also depends on working extinguishers, hydrants, alarms and an annual maintenance contract. Ask Munshi Fire Safety for a quote.

Sources

Facts last verified on 13 November 2026.

This guide is general information, not legal advice. Rules, forms and fees change, and the Gujarat Fire Safety Compliance Portal prevails over any summary. Confirm your case with the fire authority, a Licensed Agency or a lawyer before you act.