Records a Fire Inspector Will Ask For in Gujarat

Compliance in practiceLast verified: 2 min read

An inspector or auditor in Gujarat will expect to see the Fire Safety Certificate with its renewals and declarations, the three self-certifications, the AMC and service reports, system test certificates, current drawings, maintenance logs, an extinguisher register, mock drill records and evacuation plans. Missing or expired test certificates and drawings that do not match the installation are the most common gaps.

Certificate forms
B13, B13.3, B2, B15
Self-certifications
No alteration, AMC, electrical safety
Drills
Twice a year, with a record
Evacuation plans
On every floor

The records checklist

  • The Fire Safety Certificate, the current renewal and the declarations (Forms B13, B13.3, B2, B15).
  • The three self-certifications: no alteration, an AMC for fire equipment, and safe electrical installation.
  • The AMC contract and service reports.
  • Test certificates for sprinkler (IS 15105), detection and alarm (IS 2189), fire pump performance, and wet riser and hydrant flow.
  • An independent fire safety audit report, where one is used.
  • As-built drawings that match the installation, and up-to-date fire drawings including damper locations.
  • Maintenance logs, the extinguisher register and the fire safety management plan.
  • Mock drill records and the schedule.
  • Evacuation route plans on every floor and exit signage in working order.
  • The Fire Safety Executive appointment letter where Regulation 27 applies.

Common gaps

One audit vendor lists the usual deficiencies as: missing or expired system test certificates, drawings that do not match the installed system, no maintenance logs, no fire safety management plan, and no hydrant test certificate. Gujarat does not name specific logbook formats in the sources we have read, so a dated register and logs in a consistent format are the safest practice.

Keeping records useful

  • One folder per year, with scans in a shared drive and originals on site.
  • Service reports with date, items checked, defects and actions.
  • Ask each supplier for the licence details of the products you buy and keep them on file.
  • Link the register to the compliance calendar so renewals and drills are not missed.

Common questions

What documents does a fire officer check during an inspection?

The certificate and renewals, self-certifications, AMC and service reports, test certificates, drawings, maintenance logs, extinguisher register, mock drill records and evacuation plans.

Is an AMC mandatory in Gujarat?

The certificate application requires a self-certification that an AMC for fire protection equipment is in place.

More questions? See the fire safety FAQ for short answers on certificates, renewal, penalties, extinguishers and pandals.

Maintenance with paperwork

Munshi Fire Safety can provide inspection and maintenance with service reports and dated records. Tell us what documentation you need for renewal.

Sources

  • Gujarat Fire Prevention and Life Safety Measures Regulations, 2023 (Gazette Extraordinary, 13 December 2023), amended 24 June 2024
  • Gujarat Fire Prevention and Life Safety Measures Rules, 2014, with amendments to 2026
  • Gujarat Fire Safety Compliance Portal (gujfiresafetycop.in)
  • Audit-vendor lists of common deficiencies (indicative)

Facts last verified on 13 November 2026.

This guide is general information, not legal advice. Rules, forms and fees change, and the Gujarat Fire Safety Compliance Portal prevails over any summary. Confirm your case with the fire authority, a Licensed Agency or a lawyer before you act.